How to Calculate Cement, Sand and Aggregate for 1 m³ of M20 Concrete
Before every concrete pour, someone on site asks the same question: how much cement, sand and aggregate do we need? If you know one simple method, you can answer it in two minutes. Let’s work it out for 1 cubic metre of M20 concrete.
What you need to know first
- M20 nominal mix ratio: 1 : 1.5 : 3 (cement : sand : aggregate)
- Dry volume factor: 1.54
- Volume of one cement bag (50 kg): 0.0347 m³
- Density of cement: 1440 kg/m³
Why multiply by 1.54?
Dry materials have air gaps between the particles. When water is added, the fine material fills those gaps and the total volume shrinks. So to get 1 m³ of wet concrete, you need about 1.54 m³ of dry material. Some engineers use 1.52 or 1.57, but 1.54 is the common site value.
Step-by-step calculation
Step 1: Dry volume
Dry volume = 1 × 1.54 = 1.54 m³
Step 2: Sum of the ratio
1 + 1.5 + 3 = 5.5
Step 3: Cement
Cement = 1.54 × 1/5.5 = 0.28 m³
In bags = 0.28 ÷ 0.0347 = about 8 bags
In kg = 0.28 × 1440 = about 403 kg
Step 4: Sand
Sand = 1.54 × 1.5/5.5 = 0.42 m³
Step 5: Aggregate
Aggregate = 1.54 × 3/5.5 = 0.84 m³
Step 6: Water
With a water-cement ratio of 0.5, water = 0.5 × 403 = about 200 litres
Quick summary for 1 m³ of M20
| Material | Quantity |
|---|---|
| Cement | About 8 bags (403 kg) |
| Sand | 0.42 m³ |
| Aggregate | 0.84 m³ |
| Water | About 200 litres (w/c 0.5) |
Example: a 4 m × 5 m slab, 125 mm thick
Volume = 4 × 5 × 0.125 = 2.5 m³
Cement = 2.5 × 8.07 = about 20 bags
Sand = 2.5 × 0.42 = 1.05 m³
Aggregate = 2.5 × 0.84 = 2.1 m³
Add 2-5% for wastage, depending on site conditions.
Other common nominal mixes
| Grade | Ratio | Cement per m³ (approx.) |
|---|---|---|
| M10 | 1 : 3 : 6 | About 4.4 bags |
| M15 | 1 : 2 : 4 | About 6.3 bags |
| M20 | 1 : 1.5 : 3 | About 8 bags |
Important note
These are nominal mix values for estimation. For M25 and above, and on most large projects, concrete is made to a design mix from lab tests, and those quantities take priority. Always follow the project specification.