How to Calculate Cement, Sand and Aggregate for 1 m³ of M20 Concrete

Before every concrete pour, someone on site asks the same question: how much cement, sand and aggregate do we need? If you know one simple method, you can answer it in two minutes. Let’s work it out for 1 cubic metre of M20 concrete.

What you need to know first

  • M20 nominal mix ratio: 1 : 1.5 : 3 (cement : sand : aggregate)
  • Dry volume factor: 1.54
  • Volume of one cement bag (50 kg): 0.0347 m³
  • Density of cement: 1440 kg/m³

Why multiply by 1.54?

Dry materials have air gaps between the particles. When water is added, the fine material fills those gaps and the total volume shrinks. So to get 1 m³ of wet concrete, you need about 1.54 m³ of dry material. Some engineers use 1.52 or 1.57, but 1.54 is the common site value.

Step-by-step calculation

Step 1: Dry volume

Dry volume = 1 × 1.54 = 1.54 m³

Step 2: Sum of the ratio

1 + 1.5 + 3 = 5.5

Step 3: Cement

Cement = 1.54 × 1/5.5 = 0.28 m³
In bags = 0.28 ÷ 0.0347 = about 8 bags
In kg = 0.28 × 1440 = about 403 kg

Step 4: Sand

Sand = 1.54 × 1.5/5.5 = 0.42 m³

Step 5: Aggregate

Aggregate = 1.54 × 3/5.5 = 0.84 m³

Step 6: Water

With a water-cement ratio of 0.5, water = 0.5 × 403 = about 200 litres

Quick summary for 1 m³ of M20

Material Quantity
Cement About 8 bags (403 kg)
Sand 0.42 m³
Aggregate 0.84 m³
Water About 200 litres (w/c 0.5)

Example: a 4 m × 5 m slab, 125 mm thick

Volume = 4 × 5 × 0.125 = 2.5 m³
Cement = 2.5 × 8.07 = about 20 bags
Sand = 2.5 × 0.42 = 1.05 m³
Aggregate = 2.5 × 0.84 = 2.1 m³

Add 2-5% for wastage, depending on site conditions.

Other common nominal mixes

Grade Ratio Cement per m³ (approx.)
M10 1 : 3 : 6 About 4.4 bags
M15 1 : 2 : 4 About 6.3 bags
M20 1 : 1.5 : 3 About 8 bags

Important note

These are nominal mix values for estimation. For M25 and above, and on most large projects, concrete is made to a design mix from lab tests, and those quantities take priority. Always follow the project specification.

For a full guide to quantities and costing, see the Estimation & Costing E-Book. The Quantity Survey Handbook is a handy quick reference on site.

Choosing your next book? See our guide to the best construction e-books for civil engineers.

Comments (0)


Leave a Reply

Your email address will not be published. Required fields are marked *

🪔 ये Diwali Notes वाली | Complete Notes Pack ₹1,299 | Any 3 E-Books ₹399 →